In rufiyaa
2020
2021
2022
2023
2024
Actual
Revised
Budgeted
Budgeted
Budgeted
Total
-
3,823,995
19,148,734
38,257,944
78,220,469
Construction Of Magistrate Court - Th.Guraidhoo
Ongoing Th. Guraidhoo
-
1,493,145
1,210,456
83,288
-
Construction Of Magistrate Court - HA.Baarah
Ongoing HA. Baarah
-
1,265,990
685,322
440,447
118,712
Construction Of Magistrate Court - GDh.Vaadhoo
Ongoing GDh. Vaadhoo
-
1,064,860
1,210,456
83,378
-
Construction Of Magistrate Court - K.Hura
Tendering K. Huraa
-
-
360,000
680,616
677,000
Construction Of Niyaavehi (10 Storey Building)
Tendering Male' City
-
-
5,000,000
8,978,013
44,821,745
Construction Of Magistrate Court - M.Veyvah
Pre-Tendering M. Veyvah
-
-
360,000
680,616
677,000
Construction Of Magistrate Court - R.Angolhitheemu
Pre-Tendering R. Angolhitheemu
-
-
200,000
360,000
971,391
Construction Of Court Complex Building - Addu City
Pre-Tendering S. Hithadhoo
-
-
3,622,500
6,848,696
6,812,310
Estab. Of Supreme Court New Building
Pre-Tendering Male' City
-
-
1,500,000
10,102,890
14,142,311
Const. Of Magistrate Court - Multiple Islands
New Multiple Islands
-
-
5,000,000
10,000,000
10,000,000
Total
In Million Rufiyaa