In rufiyaa
2020
2021
2022
2023
2024
Actual
Revised
Budgeted
Budgeted
Budgeted
Total
8,829,556
26,930,249
17,238,352
21,847,628
51,381,372
Developing Airpoirt - Faresmaathoda
Ongoing Ministry of National Planning, Housing and Infrastructure Domestic
13,030
26,839,582
12,118,481
13,213,410
20,360,646
Developing Harbour - GDh.Faresmaathoda
Pre-Tendering Ministry of National Planning, Housing and Infrastructure Domestic
368,864
-
200,000
2,267,156
18,730,168
Land Reclamation For Airport - GDh.Faresmaathoda
Regional Airports Domestic
7,456,385
-
-
-
-
Dev. of Wetland Park Area - GDh.Faresmaathoda
Ministry of National Planning, Housing and Infrastructure India Fund
536,277
90,667
-
-
-
Repairing Fence of Futsal Ground - GDh.Faresmaathonda
Ministry of Youth, Sports & Community Empowerment Domestic
455,000
-
-
-
-
Road Const.Airport to Habor-Faresmathoda
Pre-Tendering Ministry of National Planning, Housing and Infrastructure Domestic
-
-
300,000
567,180
564,166
Development of Causeway - GDh.Faresmaathodaa
Awarded Ministry of National Planning, Housing and Infrastructure Domestic
-
-
2,957,371
2,795,602
6,953,762
School 05 Class Room & Multi Purpose Hall - GDh.Rathafandhoo
New Ministry of Education Domestic
-
-
1,462,500
2,765,001
2,750,312
Devel. Of Youth Centre - GDh.Faresmaathoda
Pre-Tendering Ministry of Youth, Sports & Community Empowerment Domestic
-
-
200,000
239,279
2,022,318
Total
In Million Rufiyaa
Breakdown for year: 2022